A study
conducted by Infrastructure & Project Monitoring Division of Ministry of
Statistics and Programme Implementation reports that out of 860 central sector
projects (which are of the order of more than Rs.204.2 million) costing around
Rs.3432 trillion and average project duration of 6 to 7 years, about 35% are
behind schedule and the delay ranges from 1 to 195 months. Time
and cost overruns are a result of delays in project execution. Some of the
reasons advanced for these delays and subsequent overruns in time are inclement
weather, shortage in labour and material supply, sub-contractors, changes after
contract execution has commenced, poor site management and government policies.
The delay in a project is also due to the poorly drafted contract clauses.
Identification of the contract clauses that affect the schedule of the
construction project was which taken up by CPWD has been carried out in this
study.
Download the Complete Article - Here
Download the Complete Article -
No comments:
Post a Comment